Monday, August 10, 2009

Day - 58 Stick Work







The guys began work on the vent on the gable of the parking shelter early this morning. They are recreating the look of the existing house gables with the addition of a cool vent that we will duplicate on the main gable over the porch of the existing house. Lots of cutting here and precise work to make such a neat design. The guys were joined today be the plumbers, the electricians and even the painters. The painters put up the first coat of primer on the trim on the front of the car shelter. The electricians began work running wire on the main floor of the addition and the plumbers continued work on the vent pipes and also on the supply line for the ice maker that will be in the kitchenette. Finally you can see from the photos that the guys are preparing a scaffolding to use to install the siding.